Asante Gold Ramps up new Sulphide Treatment Plant at Bibiani, Gold Recovery Surpasses 90%
Asante Gold Corporation has announced significant progress in the ramp-up of its newly constructed sulphide treatment plant (STP) at the Bibiani Gold Mine in Ghana, marking what the company describes as a major step forward in its long-term production growth strategy.
In an operational update released on Monday, the company confirmed that construction and commissioning of the STP have been completed, with plant operations beginning on a 12-hour basis on September 27, 2025. Continuous, round-the-clock operations were achieved two days later on September 29.
According to the company, process optimization advanced steadily through late November despite delays in delivery of a critical oxygen plant, initially scheduled to arrive in September but only delivered in late November. The oxygen plant came online on December 3, enabling the Aachen Reactor to operate as designed.
As a result, gold recovery at the STP has risen sharply — improving from 60% at start-up to above 90% currently, with overall plant recovery now at 82%. Asante said it continues to adjust operating parameters, including reagent addition practices, to push overall recoveries above 90% in the near term. The plant remains on track to reach its targeted ~92% overall recovery, consistent with pilot testwork.
The STP has a nameplate processing capacity of about 4 million tonnes per year, or roughly 12,000 tonnes per day, supporting plans to expand the mine’s processing capacity from 3.2 million tonnes annually.
Commenting on the progress, Asante’s President and CEO, David Anthony, noted that the ramp-up marks an important milestone for the Bibiani operation. “The sulphide treatment plant is now running continuously and optimization is well underway. This is a pivotal step in Bibiani’s growth profile. As gold recovery moves toward our ~92% target and throughput rises to 4M tonnes per year, we expect meaningful improvements in gold production and unit costs at Bibiani,” he stated.
Operational focus areas
The company said its operating team has concentrated on a controlled ramp-up that emphasizes throughput stability, reagent efficiency and achieving stronger gold liberation through regrinding.
Key priorities in the coming months include:
Sustaining 24/7 operations while optimizing flotation kinetics, concentrate regrind and carbon-in-pulp (CIP) performance;
Achieving the targeted ~92% gold recovery and increasing throughput toward the 4 million tonnes per year design by Q2 2026; and
Processing higher-grade ore now being mined from the Main Pit in line with mine sequencing, resulting in rising gold output.
The technical information in the update was reviewed and approved by David Anthony, P.Eng., a qualified person under NI 43-101.
Asante Gold operates the Bibiani and Chirano Gold Mines and continues advanced technical studies at its Kubi Gold Project. The company also holds exploration interests at Keyhole, Fahiakoba and Betenase, all located along Ghana’s prolific Bibiani and Ashanti belts.